Oyster superyachts take shape at RMK Marine

The first two Oyster Superyachts designed by Dubois are starting to take shape at the RMK Marine facility in Tuzla, Turkey.

photo 126789

The Oyster 100 is the first of these to go into production and it is progressing well in the new purpose built facility. Currently the mould is being prepared to infuse the first hull and tests were recently successfully carried out on a full size test infusion of a 3m hull through midship section. The hull moulding is expected to be completed by April when RMK Marine will start to fit the engine and stern gear.

All system drawings are at Lloyds for approval and the purchasing of all main equipment is well advanced.

photo 126790

The Oyster 125 hull plug has been made and is currently being filled and faired. The deck plug is in progress and due for completion shortly.

RMK Marine currently has the Sparkman & Stephens 52m Ketch Nazenin V nearing completion plus a new build motor yacht project as well as an extensive list of refit projects.